Wrong to amend development plans after signing S&P, rules court - Hello loyal readers FeedGoogle, In the article you are reading this time with the title Wrong to amend development plans after signing S&P, rules court, We have prepared this article well for you to read and take information in it. hopefully the contents of the post Article Malaysians, what we write you can understand. Alright, happy reading.



Title : Wrong to amend development plans after signing S&P, rules court
Category : Malaysians

Read also:


Wrong to amend development plans after signing S&P, rules court

The court agreed with the buyers of units at Princess Cove that the developer had deprived them of late delivery penalty by amending the original development plan.JOHOR BAHRU: Amending development plans after the sale and purchase agreement is signed is a breach of the contract, the High Court has ruled in a class action brought against a developer by 145 buyers of luxury condominium units here.In its decision handed out on Monday, the court agreed with the purchasers of condominium units at Princess Cove that the developer ought to have obtained their consent before amending the original plan of Phase 1 in the S&P into Phase 1a and 1b.Under Phase 1, there were supposed to be seven blocks together with a shopping mall. However, after the amendment, only three residential blocks were completed first without the others as stated in the S&P.The court also concurred with t…

The court agreed with the buyers of units at Princess Cove that the developer had deprived them of late delivery penalty by amending the original development plan.JOHOR BAHRU: Amending development plans after the sale and purchase agreement is signed is a breach of the contract, the High Court has ruled in a class action brought against a developer by 145 buyers of luxury condominium units here.In its decision handed out on Monday, the court agreed with the purchasers of condominium units at Princess Cove that the developer ought to have obtained their consent before amending the original plan of Phase 1 in the S&P into Phase 1a and 1b.Under Phase 1, there were supposed to be seven blocks together with a shopping mall. However, after the amendment, only three residential blocks were completed first without the others as stated in the S&P.The court also concurred with t…


That's the article Wrong to amend development plans after signing S&P, rules court

That's it for the article Wrong to amend development plans after signing S&P, rules court this time, hopefully can be useful for all of you. well, see you in another article post.


You are now reading the article Wrong to amend development plans after signing S&P, rules court with link address https://feedgoogle.blogspot.com/2021/08/wrong-to-amend-development-plans-after.html